Second fault on 'Squinty Bridge' | Second fault on 'Squinty Bridge' |
(about 3 hours later) | |
A crack has been found on Glasgow's Clyde Arc bridge just over a week after a support cable snapped. | A crack has been found on Glasgow's Clyde Arc bridge just over a week after a support cable snapped. |
The £20m crossing, known locally as the Squinty Bridge, was closed while repairs were ongoing and the crack was found during an inspection. | The £20m crossing, known locally as the Squinty Bridge, was closed while repairs were ongoing and the crack was found during an inspection. |
It is expected that it will be closed for six months, rather than a couple of weeks as had been initially anticipated by engineers. | It is expected that it will be closed for six months, rather than a couple of weeks as had been initially anticipated by engineers. |
The River Clyde has now also been shut to all traffic travelling below it. | The River Clyde has now also been shut to all traffic travelling below it. |
Glasgow City Council said that the crack was found in a similar component to the one which failed and was removed last week. | Glasgow City Council said that the crack was found in a similar component to the one which failed and was removed last week. |
Impact unclear | Impact unclear |
Though the bridge was designed to allow for the removal of one of these supports, the impact of the failure of the second is still unclear. | Though the bridge was designed to allow for the removal of one of these supports, the impact of the failure of the second is still unclear. |
The cable, one of 14 which supports the newest bridge over the River Clyde, came crashing down on 14 January. | The cable, one of 14 which supports the newest bridge over the River Clyde, came crashing down on 14 January. |
Designers Halcrow and civil engineering contractor Edmund Nuttall Ltd, who built the bridge, are investigating the cause of the problems. | Designers Halcrow and civil engineering contractor Edmund Nuttall Ltd, who built the bridge, are investigating the cause of the problems. |
The bridge between Finnieston and Pacific Quay opened in 2006 and is still under contractor guarantee. | The bridge between Finnieston and Pacific Quay opened in 2006 and is still under contractor guarantee. |
The cables are an integral part of the bridge structure | |
The structure, which spans 140m, is a tied arch design, carrying four traffic lanes. One lane in each direction is reserved for public transport and there are pedestrian and cycle paths. | The structure, which spans 140m, is a tied arch design, carrying four traffic lanes. One lane in each direction is reserved for public transport and there are pedestrian and cycle paths. |
Running at an angle across the water, it was the first new road bridge over the river to be built since 1969 when it was built at a cost of £20.3m. | Running at an angle across the water, it was the first new road bridge over the river to be built since 1969 when it was built at a cost of £20.3m. |
A spokesman for Glasgow City Council said public safety was its number one priority and apologised for the inconvenience. | A spokesman for Glasgow City Council said public safety was its number one priority and apologised for the inconvenience. |
"The bridge was closed last week following the failure of a steel component that connected one of the hangers to the arch," he added. | |
"The casting that failed has been taken away for inspection and testing and the council, constructors and designers are still awaiting the results of this. | |
"In the course of an inspection today, a crack was found in another similar connector on a different hanger. | |
"The council has, as a precautionary measure, requested that all river traffic below the bridge be suspended until further notice." |