This article is from the source 'bbc' and was first published or seen on . It last changed over 40 days ago and won't be checked again for changes.
You can find the current article at its original source at http://www.bbc.co.uk/news/uk-northern-ireland-31713687
The article has changed 2 times. There is an RSS feed of changes available.
Previous version
1
Next version
Version 0 | Version 1 |
---|---|
Gas to the West scheme set for Enniskillen launch | Gas to the West scheme set for Enniskillen launch |
(about 4 hours later) | |
A project to connect around 40,000 homes and businesses to the gas network will be formally launched in Enniskillen on Wednesday. | A project to connect around 40,000 homes and businesses to the gas network will be formally launched in Enniskillen on Wednesday. |
The Gas to the West scheme will cost around £250m, including a grant of up to £32m from the NI Executive. | The Gas to the West scheme will cost around £250m, including a grant of up to £32m from the NI Executive. |
The project will be built and operated by Mutual Energy and Scotia Gas Networks (SGN). | The project will be built and operated by Mutual Energy and Scotia Gas Networks (SGN). |
Construction work is due to start later this year, with Strabane being the first town connected by late 2016. | Construction work is due to start later this year, with Strabane being the first town connected by late 2016. |
A pipeline running from Portadown will be the second phase of the project linking Magherafelt, Cookstown, Coalisland, Dungannon, Omagh and Enniskillen. | A pipeline running from Portadown will be the second phase of the project linking Magherafelt, Cookstown, Coalisland, Dungannon, Omagh and Enniskillen. |
The final phase will involve extending the pipeline from Enniskillen to Derrylin. | The final phase will involve extending the pipeline from Enniskillen to Derrylin. |
The construction work is due to be completed by 2017. | |
It will involve approximately 200km of pipeline linking the towns to the existing network and 500km of gas mains and services within the towns. | It will involve approximately 200km of pipeline linking the towns to the existing network and 500km of gas mains and services within the towns. |
Cost | Cost |
The construction phase should provide work for around 200 people. | The construction phase should provide work for around 200 people. |
Enterprise Minister Arlene Foster said: "This hugely important project will extend the natural gas network to Strabane, Omagh, Enniskillen, Derrylin, Dungannon, Coalisland, Cookstown and Magherafelt. | |
"It will bring greater energy choice for consumers and increase the potential for businesses and the public sector to use a cleaner more efficient fuel. | |
"With natural gas being the cleanest burning fossil fuel, extending the gas network will help us achieve our greenhouse gas emissions target." | |
Mutual Energy already controls the gas pipeline between Scotland and Northern Ireland, while SGN owns networks in Scotland and the south east of England. | Mutual Energy already controls the gas pipeline between Scotland and Northern Ireland, while SGN owns networks in Scotland and the south east of England. |
Customers can apply for a connection as soon as gas is available in their area. | Customers can apply for a connection as soon as gas is available in their area. |
However, the key issue of how much it will cost is still to be decided. | However, the key issue of how much it will cost is still to be decided. |
The companies say they are working with the Utility Regulator to agree a pricing policy. | The companies say they are working with the Utility Regulator to agree a pricing policy. |