Casement Park redevelopment: Minister acted unlawfully by granting approval Casement Park redevelopment: Minister acted unlawfully by granting approval
(35 minutes later)
Northern Ireland's environment minister acted unlawfully in approving a new GAA stadium in west Belfast, a High Court judge has ruled.Northern Ireland's environment minister acted unlawfully in approving a new GAA stadium in west Belfast, a High Court judge has ruled.
Planning permission for the 38,000-seater stadium was granted by Mark H Durkan in December 2013.Planning permission for the 38,000-seater stadium was granted by Mark H Durkan in December 2013.
Local residents who objected to the size of the planned development launched a legal challenge in response.Local residents who objected to the size of the planned development launched a legal challenge in response.
Mr Justice Horner held the decision making process around the decision was "fundamentally flawed".Mr Justice Horner held the decision making process around the decision was "fundamentally flawed".
Bigger crowds
He identified failures in the environmental impact assessment of the increased facilities and an unrealistic reliance by the Department of the Environment (DoE) on an existing 32,600 capacity as a baseline for the project.He identified failures in the environmental impact assessment of the increased facilities and an unrealistic reliance by the Department of the Environment (DoE) on an existing 32,600 capacity as a baseline for the project.
With far fewer spectators normally attending matches at the current ground, the judge also found that the effect of bigger crowds on the surrounding roads network had not been properly examined.With far fewer spectators normally attending matches at the current ground, the judge also found that the effect of bigger crowds on the surrounding roads network had not been properly examined.
However, he did not quash the minister's decision.However, he did not quash the minister's decision.
Instead, lawyers for the DoE, the GAA and a residents group who mounted the legal challenge are to make further submissions on appropriate remedies.Instead, lawyers for the DoE, the GAA and a residents group who mounted the legal challenge are to make further submissions on appropriate remedies.
'Deeply disappointed'
Local residents claimed the proposed £76m stadium would be too big for the area.Local residents claimed the proposed £76m stadium would be too big for the area.
Tom Daly, chairman of the Casement Park Project Board said they were "deeply disappointed" by the decision. Tom Daly, chairman of the Casement Park Project Board, said they were "deeply disappointed" by the decision.
"The proposed redevelopment of Casement Park would have provided the opportunity of a world class provincial stadium for the GAA and the broader community in the heart of Belfast."The proposed redevelopment of Casement Park would have provided the opportunity of a world class provincial stadium for the GAA and the broader community in the heart of Belfast.
"The project would also have provided much needed economic and social benefits to west Belfast and beyond, including financial investment, new jobs, apprenticeships and community projects."The project would also have provided much needed economic and social benefits to west Belfast and beyond, including financial investment, new jobs, apprenticeships and community projects.
"Over the coming weeks we will reflect on this decision and consider what the next steps are for Casement Park.""Over the coming weeks we will reflect on this decision and consider what the next steps are for Casement Park."
The GAA's provincial body, the Ulster Council, said a 38,000 capacity was needed for the staging of Ulster Senior football finals and All-Ireland quarter-finals.The GAA's provincial body, the Ulster Council, said a 38,000 capacity was needed for the staging of Ulster Senior football finals and All-Ireland quarter-finals.
The redevelopment of Casement Park is part of the government's policy to upgrade the three major sports grounds in Belfast - football's Windsor Park, Ulster's rugby ground at Ravenhill and the Gaelic games stadium at Casement.The redevelopment of Casement Park is part of the government's policy to upgrade the three major sports grounds in Belfast - football's Windsor Park, Ulster's rugby ground at Ravenhill and the Gaelic games stadium at Casement.
Three new stands have been constructed at Ravenhill.Three new stands have been constructed at Ravenhill.
Work on modernising Windsor Park, the home of Irish League club Linfield and the Northern Ireland international team, is ongoing.Work on modernising Windsor Park, the home of Irish League club Linfield and the Northern Ireland international team, is ongoing.