MoD criticised on budget forecast | MoD criticised on budget forecast |
(1 day later) | |
The Ministry of Defence has been accused of "massaging" the estimated costs of 20 of its biggest projects. | The Ministry of Defence has been accused of "massaging" the estimated costs of 20 of its biggest projects. |
It forecast a £781m saving on the Major Projects bill - but £448m of that had been moved to other military budgets, an MPs' report said. | It forecast a £781m saving on the Major Projects bill - but £448m of that had been moved to other military budgets, an MPs' report said. |
Projects are still forecast to run 11% (£2.6bn) over budget and overall delays across projects added up to 36 years. | Projects are still forecast to run 11% (£2.6bn) over budget and overall delays across projects added up to 36 years. |
The MoD said the £448m was not claimed to be an overall saving, but part of a better approach to "cost management". | The MoD said the £448m was not claimed to be an overall saving, but part of a better approach to "cost management". |
The UK spends about £6.5bn a year on 50 major defence equipment projects. | The UK spends about £6.5bn a year on 50 major defence equipment projects. |
There is no overall saving to the department as a whole as other budgets will now be hit with charges that they had not planned to cover Public Accounts Committee report | There is no overall saving to the department as a whole as other budgets will now be hit with charges that they had not planned to cover Public Accounts Committee report |
The Public Accounts Committee has been investigating cost-saving measures by the Ministry of Defence - which has faced criticism in the past for going billions of pounds over-budget, while projects ran over deadline. | The Public Accounts Committee has been investigating cost-saving measures by the Ministry of Defence - which has faced criticism in the past for going billions of pounds over-budget, while projects ran over deadline. |
The MoD introduced a review of 20 of its biggest procurement projects, for equipment like submarines and armoured vehicles, and identified ways to reduce the forecast costs of the projects by £781m overall. | The MoD introduced a review of 20 of its biggest procurement projects, for equipment like submarines and armoured vehicles, and identified ways to reduce the forecast costs of the projects by £781m overall. |
But the PAC said, of that figure, £91m was a rebate and exemption from customs, and £448m was transferred to other budgets - something the MoD said was done to make individual teams "more accountable for delivery". | But the PAC said, of that figure, £91m was a rebate and exemption from customs, and £448m was transferred to other budgets - something the MoD said was done to make individual teams "more accountable for delivery". |
'No risk' | 'No risk' |
The report said: "There is no overall saving to the department as a whole as other budgets will now be hit with charges that they had not planned to cover." | The report said: "There is no overall saving to the department as a whole as other budgets will now be hit with charges that they had not planned to cover." |
The committee's Conservative chairman Mr Leigh added: "We have no idea what cuts will have to be made to other activities of our armed forces as a result of this massaging of the figures." | The committee's Conservative chairman Mr Leigh added: "We have no idea what cuts will have to be made to other activities of our armed forces as a result of this massaging of the figures." |
Other savings were made by looking again at quantities required - for example buying fewer guided multiple launch rockets - which had proved to be more accurate than originally thought. | Other savings were made by looking again at quantities required - for example buying fewer guided multiple launch rockets - which had proved to be more accurate than originally thought. |
The MoD is nearly £3bn over budget yet still it won't hold anyone accountable for this shambles Nick HarveyLib Dem defence spokesman | |
It notes the MoD said reducing rockets and the number of support vehicles would create "no risk to operational capability". | It notes the MoD said reducing rockets and the number of support vehicles would create "no risk to operational capability". |
The report says 14 projects had reported no new delays. And of 36 new projects costing more than £20m approved since 2003 - 34 are forecast to be finished on or under budget. | The report says 14 projects had reported no new delays. And of 36 new projects costing more than £20m approved since 2003 - 34 are forecast to be finished on or under budget. |
'Toxic legacy' | 'Toxic legacy' |
But on the so-called "toxic legacy" projects - such as Astute class submarines, the Nimrod MRA4 aircraft - some dating back to the 1990s before procurement was reformed - the department was "still struggling". | But on the so-called "toxic legacy" projects - such as Astute class submarines, the Nimrod MRA4 aircraft - some dating back to the 1990s before procurement was reformed - the department was "still struggling". |
Astute class submarines are now £1bn over budget. The first of four - HMS Astute - was launched in June, nearly four years behind schedule. | Astute class submarines are now £1bn over budget. The first of four - HMS Astute - was launched in June, nearly four years behind schedule. |
Defence Minister Lord Drayson said he would study the report carefully and respond to Parliament - but said it had taken a "constructive view" of the work done on armed forces procurement. | Defence Minister Lord Drayson said he would study the report carefully and respond to Parliament - but said it had taken a "constructive view" of the work done on armed forces procurement. |
MoD - as the report makes clear - only claimed real savings on project costs Lord Drayson | MoD - as the report makes clear - only claimed real savings on project costs Lord Drayson |
He added: "To ensure project teams' performance will be assessed on costs over which they have direct control, non-programme costs have been allocated to other more appropriate areas. We have been clear that we do not claim these as savings to the department. | He added: "To ensure project teams' performance will be assessed on costs over which they have direct control, non-programme costs have been allocated to other more appropriate areas. We have been clear that we do not claim these as savings to the department. |
"This measure will help us take a more effective corporate approach to cost management. This was properly costed, and as the PAC report acknowledges this was a reasonable measure. | "This measure will help us take a more effective corporate approach to cost management. This was properly costed, and as the PAC report acknowledges this was a reasonable measure. |
"MoD - as the report makes clear - only claimed real savings on project costs." | "MoD - as the report makes clear - only claimed real savings on project costs." |
But shadow defence secretary Liam Fox accused the government of "spinning the figures to try to portray savings". | But shadow defence secretary Liam Fox accused the government of "spinning the figures to try to portray savings". |
He added: "These are horrendous overruns that inevitably impact upon our ability to run the frontline at a time when our troops are in need of extra equipment. " | He added: "These are horrendous overruns that inevitably impact upon our ability to run the frontline at a time when our troops are in need of extra equipment. " |
And Liberal Democrat defence spokesman Nick Harvey said overall delays in getting equipment to forces were now six times longer than they had been during the Second World War. | And Liberal Democrat defence spokesman Nick Harvey said overall delays in getting equipment to forces were now six times longer than they had been during the Second World War. |
"The MoD is nearly £3bn over budget yet still it won't hold anyone accountable for this shambles," he said. | "The MoD is nearly £3bn over budget yet still it won't hold anyone accountable for this shambles," he said. |