London Olympics could cost £9bn | London Olympics could cost £9bn |
(about 8 hours later) | |
The cost of the 2012 London Olympics could rise to nearly four times the figure set out in the city's bid for the Games, the BBC has learned. | The cost of the 2012 London Olympics could rise to nearly four times the figure set out in the city's bid for the Games, the BBC has learned. |
The Treasury and the Department for Culture, Media and Sport are discussing a price of £9bn - up from the £2.35bn set out in London's bid document. | The Treasury and the Department for Culture, Media and Sport are discussing a price of £9bn - up from the £2.35bn set out in London's bid document. |
The government believes construction alone could cost £3.3bn, with an extra £2bn allocated as a contingency fund. | The government believes construction alone could cost £3.3bn, with an extra £2bn allocated as a contingency fund. |
Regeneration costs of £1.8bn and a £1bn VAT bill have also been added. | Regeneration costs of £1.8bn and a £1bn VAT bill have also been added. |
Security costs have also risen to at least £900m. | Security costs have also risen to at least £900m. |
The Shadow Culture Secretary, Hugo Swire, said the news was "staggering", and said Chancellor Gordon Brown should take responsibility, because he signed off the original budget. | |
"There is no doubt that there will be real worries across the country about the huge increase in costs... it is time we got a proper explanation from Gordon Brown on what has gone on and assurances as to what the government is doing to control the ever-increasing budget," he said. | |
In the wake of heavy criticism of the government's handling of the games, Culture Secretary Tessa Jowell admitted to parliament in November that the cost of the Games would rise by £900m - 40% - to £3.3bn. | In the wake of heavy criticism of the government's handling of the games, Culture Secretary Tessa Jowell admitted to parliament in November that the cost of the Games would rise by £900m - 40% - to £3.3bn. |
But critics have continued to express wide-ranging concerns about planning, over everything from transport to the burden on the tax payer and effect on the National Lottery's funding of good causes in order to meet costs. | But critics have continued to express wide-ranging concerns about planning, over everything from transport to the burden on the tax payer and effect on the National Lottery's funding of good causes in order to meet costs. |
Decontamination work | Decontamination work |
The Treasury's insistence on how the budget is drawn up is thought to have considerably added to the costs of the games. | The Treasury's insistence on how the budget is drawn up is thought to have considerably added to the costs of the games. |
It is understood it now insisting a 60% contingency should be to be added to the construction cost. | It is understood it now insisting a 60% contingency should be to be added to the construction cost. |
But this figure has been resisted both by the Mayor of London Ken Livingstone and also the DCMS. | But this figure has been resisted both by the Mayor of London Ken Livingstone and also the DCMS. |
Both of them would like a much lower contingency, a view that appears to have support from CLM, the Delivery Partners. | Both of them would like a much lower contingency, a view that appears to have support from CLM, the Delivery Partners. |
A variety of other factors are also at play. | A variety of other factors are also at play. |
These include rise in commodity prices, adjustments to transport figures to reflect 2012 prices and a revised estimate for inflation on construction costs. | These include rise in commodity prices, adjustments to transport figures to reflect 2012 prices and a revised estimate for inflation on construction costs. |
The land in the east end of London chosen for the site also needs decontamination and major remedial work before it can be fit for the games. | The land in the east end of London chosen for the site also needs decontamination and major remedial work before it can be fit for the games. |
The Treasury has also decided that the Olympic Development Authority will have to pay VAT. | The Treasury has also decided that the Olympic Development Authority will have to pay VAT. |
While VAT is in effect paid to the Treasury, the cash initially still has to be found before it is reclaimed. | While VAT is in effect paid to the Treasury, the cash initially still has to be found before it is reclaimed. |