Scotland's ferries saga ship to finally set sail Scotland's ferries saga ship to finally set sail
(about 5 hours later)
The ship at the centre of Scotland's long-running ferries saga is scheduled to make its first passenger voyage before dawn on Monday. The ship at the centre of Scotland's long-running ferries saga is due to make its first scheduled passenger voyage before dawn on Monday.
MV Glen Sannox is due to leave Troon harbour in South Ayrshire, bound for the Isle of Arran, on its first sailing at 06:30. MV Glen Sannox is expected to leave Troon harbour in South Ayrshire, bound for the Isle of Arran, at 06:30.
But a yellow alert, external, issued by Caledonian MacBrayne on Sunday, said it may be subject to delay or cancellation due to high winds.But a yellow alert, external, issued by Caledonian MacBrayne on Sunday, said it may be subject to delay or cancellation due to high winds.
The ship - which was meant to be delivered almost seven years ago - completed a return test sailing on Sunday and is the first new large vessel to join the UK's largest ferry fleet in nearly a decade.The ship - which was meant to be delivered almost seven years ago - completed a return test sailing on Sunday and is the first new large vessel to join the UK's largest ferry fleet in nearly a decade.
With a capacity for 127 cars and 852 passengers, Glen Sannox will help relieve pressures on the state-owned operator which has struggled in recent years to maintain services with ageing and increasingly unreliable vessels.With a capacity for 127 cars and 852 passengers, Glen Sannox will help relieve pressures on the state-owned operator which has struggled in recent years to maintain services with ageing and increasingly unreliable vessels.
The Glen Sannox completed a test sailing on Sunday ahead of its first passenger crossing on Monday The Glen Sannox completed a test sailing on Sunday ahead of its first scheduled passenger crossing on Monday
The orders for the dual-fuel ships Glen Sannox and its sister vessel Glen Rosa, were placed with the Ferguson shipyard in Port Glasgow nearly a decade ago.The orders for the dual-fuel ships Glen Sannox and its sister vessel Glen Rosa, were placed with the Ferguson shipyard in Port Glasgow nearly a decade ago.
But acrimonious disputes over the design challenges and claims for extra costs saw the shipyard fall into administration and nationalised in 2019.But acrimonious disputes over the design challenges and claims for extra costs saw the shipyard fall into administration and nationalised in 2019.
The ships have ended up costing more than four times the £97m contract price and sparked arguably the longest running political row of the devolution era.The ships have ended up costing more than four times the £97m contract price and sparked arguably the longest running political row of the devolution era.
CalMac chief executive Duncan Mackison said staff had worked hard to complete sea trials and crew familiarisation for the first gas-powered ferry built in the UK.CalMac chief executive Duncan Mackison said staff had worked hard to complete sea trials and crew familiarisation for the first gas-powered ferry built in the UK.
"We are excited to welcome people on board and look forward to seeing a vessel which will bring great benefit to Arran enter service for the local community," he said."We are excited to welcome people on board and look forward to seeing a vessel which will bring great benefit to Arran enter service for the local community," he said.
Named after an Arran beauty spot, Glen Sannox will make three return sailings from Troon to the island's main town of Brodick each day.Named after an Arran beauty spot, Glen Sannox will make three return sailings from Troon to the island's main town of Brodick each day.
An identical vessel, Glen Rosa - still under construction at the Ferguson shipyard in Port Glasgow - is due to join it on the route at the end of the year, although it was reported at the weekend that a new six-month delay will be announced shortly., external An identical vessel, Glen Rosa - still under construction at the Ferguson shipyard in Port Glasgow - is due to join it on the route at the end of the year, although it was reported at the weekend that a new delay will be announced shortly., external
On Sunday Glen Sannox carried passengers and vehicles on her maiden voyage after completing a test run. On Sunday Glen Sannox carried its first passengers and vehicles when it was unexpectedly switched for the scheduled vessel for one return sailing, in a test run ahead of Monday's full timetable.
Mr Mackison said: "A massive effort has gone into getting MV Glen Sannox to this stage, and everyone at CalMac is excited to have her in the fleet and serving Arran."Mr Mackison said: "A massive effort has gone into getting MV Glen Sannox to this stage, and everyone at CalMac is excited to have her in the fleet and serving Arran."
For residents on the island the arrival of the new ship should bring relief after years of transport uncertainty.For residents on the island the arrival of the new ship should bring relief after years of transport uncertainty.
Mike Dobson, from Arran Cancer Support, says the uncertainty has taken a toll on the mental health of those needing regular mainland medical treatmentMike Dobson, from Arran Cancer Support, says the uncertainty has taken a toll on the mental health of those needing regular mainland medical treatment
Mike Dobson, chairman of Arran Cancer Support, said it had been particularly difficult for those needing hospital treatment on the mainland.Mike Dobson, chairman of Arran Cancer Support, said it had been particularly difficult for those needing hospital treatment on the mainland.
"An ageing ferry fleet with lots of technical or weather-related problems has made it more difficult for people to feel that they are going to get there," he told BBC News."An ageing ferry fleet with lots of technical or weather-related problems has made it more difficult for people to feel that they are going to get there," he told BBC News.
"It's meant more cancellations of appointments and that bears a certain weight on people and affects their mental health.""It's meant more cancellations of appointments and that bears a certain weight on people and affects their mental health."
Sheila Gilmore, from Visit Arran, said businesses had also been badly affected, but she was optimistic visitor numbers will now start to recover.Sheila Gilmore, from Visit Arran, said businesses had also been badly affected, but she was optimistic visitor numbers will now start to recover.
"We are very hopeful, it's been a long struggle to get here but we have to look forward and put what is in the past behind us," she said."We are very hopeful, it's been a long struggle to get here but we have to look forward and put what is in the past behind us," she said.
Scotland's entire west coast ferry network should also benefit as the average age of the fleet falls and new capacity allows vessels to be redeployed.Scotland's entire west coast ferry network should also benefit as the average age of the fleet falls and new capacity allows vessels to be redeployed.
Scotland's ferries sagaScotland's ferries saga
For SNP politicians there will be hope the arrival of Glen Sannox heralds the end of Scotland's long-running ferries controversy, although reports of new delays for Glen Rosa mean that may be premature.For SNP politicians there will be hope the arrival of Glen Sannox heralds the end of Scotland's long-running ferries controversy, although reports of new delays for Glen Rosa mean that may be premature.
The contract to build the two ships was awarded to Ferguson's in 2015, a year after it went bust.The contract to build the two ships was awarded to Ferguson's in 2015, a year after it went bust.
It was rescued by an investment firm led by Jim McColl, an economic adviser to the then First Minister Alex Salmond. It was rescued, just before Scotland's 2014 independence referendum, by an investment firm led by Jim McColl, an economic adviser to the then First Minister Alex Salmond.
While a decade of decline had left the Clyde's last commercial shipyard with just 76 staff when it went into administration, the businessman delivered millions of pounds of investment and rapid expansion.While a decade of decline had left the Clyde's last commercial shipyard with just 76 staff when it went into administration, the businessman delivered millions of pounds of investment and rapid expansion.
But construction of the dual-fuel ships soon faltered as the firm grappled with complex design challenges while trying to hit production milestones and modernising run-down facilities.But construction of the dual-fuel ships soon faltered as the firm grappled with complex design challenges while trying to hit production milestones and modernising run-down facilities.
Claims for extra costs led to a bitter standoff between the yard's management and state-owned ferries procurement body Caledonian Maritime Assets Ltd (CMAL).Claims for extra costs led to a bitter standoff between the yard's management and state-owned ferries procurement body Caledonian Maritime Assets Ltd (CMAL).
Glen Sannox was launched with much fanfare in 2017, but the ship was far from finishedGlen Sannox was launched with much fanfare in 2017, but the ship was far from finished
Glen Sannox was launched by former first minister Nicola Sturgeon on a blustery day in November 2017, but behind the scenes a bigger political storm was brewing.Glen Sannox was launched by former first minister Nicola Sturgeon on a blustery day in November 2017, but behind the scenes a bigger political storm was brewing.
It later emerged the ship was far from finished - windows were painted on, temporary funnels were made of plywood and, more importantly, huge amounts of engineering and electrical work were still required inside.It later emerged the ship was far from finished - windows were painted on, temporary funnels were made of plywood and, more importantly, huge amounts of engineering and electrical work were still required inside.
The yard's managers blamed CMAL, claiming a poorly-developed concept design, late decision-making and interference had led to unforeseen complications.The yard's managers blamed CMAL, claiming a poorly-developed concept design, late decision-making and interference had led to unforeseen complications.
CMAL said the firm had simply underestimated the complexity of the task entrusted to it and made poor management decisions.CMAL said the firm had simply underestimated the complexity of the task entrusted to it and made poor management decisions.
The deadlock eventually saw Ferguson's run out of money and fall back into administration in 2019, with the shipyard nationalised, saving 350 jobs.The deadlock eventually saw Ferguson's run out of money and fall back into administration in 2019, with the shipyard nationalised, saving 350 jobs.
Problems continued under new "turnaround director" Tim Hair who was paid nearly £2m before a permanent chief executive was appointed in 2022.Problems continued under new "turnaround director" Tim Hair who was paid nearly £2m before a permanent chief executive was appointed in 2022.
Opposition parties, meanwhile, claimed the crisis had its roots in political opportunism and incompetence by Scottish ministers. Opposition parties, meanwhile, claimed the crisis had its roots in incompetence by Scottish ministers - which they denied.
Under new boss David Tydeman, the ships' construction eventually made progress but with more huge cost increases and repeated delays.Under new boss David Tydeman, the ships' construction eventually made progress but with more huge cost increases and repeated delays.
He was sacked by the Ferguson board last March, and the ship was finally delivered to CMAL, after several more short delays, in November.He was sacked by the Ferguson board last March, and the ship was finally delivered to CMAL, after several more short delays, in November.
Gas-powered shipsGas-powered ships
Glen Sannox is the first dual fuel ferry built in the UK capable of running on both marine gas oil (MGO), a form of diesel, and liquefied natural gas (LNG).Glen Sannox is the first dual fuel ferry built in the UK capable of running on both marine gas oil (MGO), a form of diesel, and liquefied natural gas (LNG).
When running on gas the ship's engines are quieter and emit far lower levels of exhaust pollutants known as NOx and SOx.When running on gas the ship's engines are quieter and emit far lower levels of exhaust pollutants known as NOx and SOx.
The climate change credentials of LNG, however, are questionable as the engines also release methane, which is a greenhouse gas far more potent than CO2.The climate change credentials of LNG, however, are questionable as the engines also release methane, which is a greenhouse gas far more potent than CO2.
The LNG fuel also has to be imported from Qatar and trucked up to Scotland from a terminal in Kent.The LNG fuel also has to be imported from Qatar and trucked up to Scotland from a terminal in Kent.
'Green' ferry emits more CO2 than old diesel ship'Green' ferry emits more CO2 than old diesel ship
Future of Ardrossan harbour still in limboFuture of Ardrossan harbour still in limbo
Despite being a high-sided vessel Glen Sannox is highly manoeuvrable and should be better able to cope with stormy weather conditions off Scotland's west coast.Despite being a high-sided vessel Glen Sannox is highly manoeuvrable and should be better able to cope with stormy weather conditions off Scotland's west coast.
But the size of the ship means it is currently unable to berth at Ardrossan, the closest mainland port to Arran, unless agreement is reached on a multi-million harbour redevelopment.But the size of the ship means it is currently unable to berth at Ardrossan, the closest mainland port to Arran, unless agreement is reached on a multi-million harbour redevelopment.
In addition to Glen Rosa, four other large CalMac ships are being built by a large shipyard in Turkey - though they are also delayed, by about six months.In addition to Glen Rosa, four other large CalMac ships are being built by a large shipyard in Turkey - though they are also delayed, by about six months.
The first of those ships, MV Isle of Islay, should be delivered in the spring, with the others following on about four months apart.The first of those ships, MV Isle of Islay, should be delivered in the spring, with the others following on about four months apart.