Russia’s Arctic LNG 2 project may be launched ahead of schedule – Novatek Russia’s Arctic LNG 2 project may be launched ahead of schedule – Novatek
(about 2 months later)
All three production lines of the Arctic LNG 2 plant, which is aimed at exporting liquefied natural gas (LNG) from Russia’s resource-rich Arctic region, could be launched in 2023-2025, according to gas producer Novatek.All three production lines of the Arctic LNG 2 plant, which is aimed at exporting liquefied natural gas (LNG) from Russia’s resource-rich Arctic region, could be launched in 2023-2025, according to gas producer Novatek.
The company’s CEO Leonid Mikhelson said during a meeting with Russian President Vladimir Putin on Monday that “The launch of the first line is planned for 2023, the second line in 2024, and the third line in 2025.” Novatek had earlier planned to launch the third line in 2026, Mikhelson pointed out.The company’s CEO Leonid Mikhelson said during a meeting with Russian President Vladimir Putin on Monday that “The launch of the first line is planned for 2023, the second line in 2024, and the third line in 2025.” Novatek had earlier planned to launch the third line in 2026, Mikhelson pointed out.
He also said that the company is discussing plans with Rosatom and Rosatomflot on year-round navigation along the Northern Sea Route from 2023.He also said that the company is discussing plans with Rosatom and Rosatomflot on year-round navigation along the Northern Sea Route from 2023.
The Arctic LNG 2 project on the Gydan Peninsula envisages constructing three LNG liquefaction trains of 6.6 million tons per annum each, and a cumulative gas condensate production capacity of 1.6 million tons per annum. The total LNG capacity of the three trains will be 19.8 million tons.The Arctic LNG 2 project on the Gydan Peninsula envisages constructing three LNG liquefaction trains of 6.6 million tons per annum each, and a cumulative gas condensate production capacity of 1.6 million tons per annum. The total LNG capacity of the three trains will be 19.8 million tons.
Novatek announced last month that the company had inked 20-year agreements with the shareholders of the Arctic LNG 2 on the sale and purchase of the entire produced volume of liquified natural gas.Novatek announced last month that the company had inked 20-year agreements with the shareholders of the Arctic LNG 2 on the sale and purchase of the entire produced volume of liquified natural gas.
For more stories on economy & finance visit RT's business sectionFor more stories on economy & finance visit RT's business section
Dear readers and commenters,
We have implemented a new engine for our comment section. We hope the transition goes smoothly for all of you. Unfortunately, the comments made before the change have been lost due to a technical problem. We are working on restoring them, and hoping to see you fill up the comment section with new ones. You should still be able to log in to comment using your social-media profiles, but if you signed up under an RT profile before, you are invited to create a new profile with the new commenting system.
Sorry for the inconvenience, and looking forward to your future comments,
RT Team.