Further delays on west coast line | Further delays on west coast line |
(about 2 hours later) | |
Travellers on the West Coast Main Line experienced delays for the seventh day in a row because of overhead power line problems in the Midlands. | |
The incident, in the Atherstone area of Warwickshire, resulted in delays of up to 50 minutes, the National Rail Enquiries website said. | |
However, Network Rail said the hold-ups had been less severe. | |
The route affected includes London Euston, Rugby, Stafford, Stoke-on-Trent, Crewe and Liverpool Lime Street. | |
Engineers were on site to fix a "minor problem" at Polesworth, near Tamworth, on the West Coast Main Line, Network Rail said. | Engineers were on site to fix a "minor problem" at Polesworth, near Tamworth, on the West Coast Main Line, Network Rail said. |
'Full investigation' | |
Network Rail said the West Coast line also had to be shut earlier, between Milton Keynes in Buckinghamshire and Rugby in Warwickshire after a lorry hit a railway bridge at Blisworth in Northamptonshire. | |
Trains were being diverted via Northampton, causing minor delays. | |
By late morning, the line was operating normally. | |
The line has recently been hit by overhead cable problems in Warwickshire, Buckinghamshire and Hertfordshire and a plane crash near Stafford. | The line has recently been hit by overhead cable problems in Warwickshire, Buckinghamshire and Hertfordshire and a plane crash near Stafford. |
On Tuesday night overhead power cables hit a train at Kenton in north-west London, leading to disruption for thousands of commuters on Wednesday. | On Tuesday night overhead power cables hit a train at Kenton in north-west London, leading to disruption for thousands of commuters on Wednesday. |
Disruption on the line has led to 70% of Virgin services running late since the start of the year. | Disruption on the line has led to 70% of Virgin services running late since the start of the year. |
The British Chambers of Commerce (BCC) said the line's recent £9bn upgrade was completed in haste, leading to a string of problems. | The British Chambers of Commerce (BCC) said the line's recent £9bn upgrade was completed in haste, leading to a string of problems. |
A Network Rail spokesman said a "full investigation" was being carried out into the cause of all the problems. | A Network Rail spokesman said a "full investigation" was being carried out into the cause of all the problems. |