Further delays on west coast line Further delays on west coast line
(about 2 hours later)
Travellers on the West Coast Main Line experienced delays for the seventh day in a row because of overhead wire problems in the Midlands. Travellers on the West Coast Main Line experienced delays for the seventh day in a row because of overhead power line problems in the Midlands.
The latest delay was caused by a problem in the Atherstone area of Warwickshire at about 0930 GMT, National Rail Enquiries said. The incident, in the Atherstone area of Warwickshire, resulted in delays of up to 50 minutes, the National Rail Enquiries website said.
The stations affected include London Euston, Rugby, Stafford, Stoke-on-Trent, Crewe and Liverpool Lime Street. However, Network Rail said the hold-ups had been less severe.
However, by 1100 GMT only one service was running late. The route affected includes London Euston, Rugby, Stafford, Stoke-on-Trent, Crewe and Liverpool Lime Street.
The one delay is the 1116 to Crewe, which is understood to be running 14 minutes late.
All other services are now said to be running on time, including the 1202 to London Euston.
'Full investigation'
Engineers were on site to fix a "minor problem" at Polesworth, near Tamworth, on the West Coast Main Line, Network Rail said.Engineers were on site to fix a "minor problem" at Polesworth, near Tamworth, on the West Coast Main Line, Network Rail said.
'Full investigation'
Network Rail said the West Coast line also had to be shut earlier, between Milton Keynes in Buckinghamshire and Rugby in Warwickshire after a lorry hit a railway bridge at Blisworth in Northamptonshire.
Trains were being diverted via Northampton, causing minor delays.
By late morning, the line was operating normally.
The line has recently been hit by overhead cable problems in Warwickshire, Buckinghamshire and Hertfordshire and a plane crash near Stafford.The line has recently been hit by overhead cable problems in Warwickshire, Buckinghamshire and Hertfordshire and a plane crash near Stafford.
On Tuesday night overhead power cables hit a train at Kenton in north-west London, leading to disruption for thousands of commuters on Wednesday.On Tuesday night overhead power cables hit a train at Kenton in north-west London, leading to disruption for thousands of commuters on Wednesday.
Disruption on the line has led to 70% of Virgin services running late since the start of the year.Disruption on the line has led to 70% of Virgin services running late since the start of the year.
The British Chambers of Commerce (BCC) said the line's recent £9bn upgrade was completed in haste, leading to a string of problems.The British Chambers of Commerce (BCC) said the line's recent £9bn upgrade was completed in haste, leading to a string of problems.
A Network Rail spokesman said a "full investigation" was being carried out into the cause of all the problems.A Network Rail spokesman said a "full investigation" was being carried out into the cause of all the problems.