This article is from the source 'bbc' and was first published or seen on . It last changed over 40 days ago and won't be checked again for changes.

You can find the current article at its original source at http://www.bbc.co.uk/news/uk-40453054

The article has changed 10 times. There is an RSS feed of changes available.

Version 6 Version 7
Grenfell Tower: Cladding 'changed to cheaper version' Grenfell Tower: Cladding 'changed to cheaper version'
(about 1 hour later)
Cladding fitted to Grenfell Tower during its refurbishment was changed to a cheaper version, documents obtained by the BBC suggest.Cladding fitted to Grenfell Tower during its refurbishment was changed to a cheaper version, documents obtained by the BBC suggest.
Documents show the zinc cladding originally proposed was replaced with an aluminium type, which was less fire resistant, saving nearly £300,000.Documents show the zinc cladding originally proposed was replaced with an aluminium type, which was less fire resistant, saving nearly £300,000.
The cladding is thought to have contributed to the spread of the fire that killed at least 80 people.The cladding is thought to have contributed to the spread of the fire that killed at least 80 people.
Kensington and Chelsea Council insists fire safety was not compromised.Kensington and Chelsea Council insists fire safety was not compromised.
It comes as the council's first cabinet meeting since the disaster was adjourned after just 20 minutes on Thursday - after it was forced by a court order to admit the press and public.It comes as the council's first cabinet meeting since the disaster was adjourned after just 20 minutes on Thursday - after it was forced by a court order to admit the press and public.
The council halted the meeting, claiming it would "prejudice" the forthcoming public inquiry.The council halted the meeting, claiming it would "prejudice" the forthcoming public inquiry.
However, Downing Street has criticised the council, saying the High Court had ruled the meeting should be open to the public.However, Downing Street has criticised the council, saying the High Court had ruled the meeting should be open to the public.
"We would have expected the council to respect that," a spokesman added."We would have expected the council to respect that," a spokesman added.
Meanwhile, the head of the Kensington and Chelsea Tenant Management Organisation has stepped aside so he can focus on "assisting with the investigation and inquiry".
The company, which manages Grenfell Tower on behalf of the council, said it will appoint an interim chief executive to replace Robert Black.
The documents obtained by the BBC reveal contractors working for Kensington and Chelsea council were asked in 2014 to replace zinc cladding with a more economical aluminium version.The documents obtained by the BBC reveal contractors working for Kensington and Chelsea council were asked in 2014 to replace zinc cladding with a more economical aluminium version.
One document - a list of requested savings sent to contractors in July 2014 - details potential savings of £693,161, reducing the cost of the contract from about £9.2m to £8.5m.One document - a list of requested savings sent to contractors in July 2014 - details potential savings of £693,161, reducing the cost of the contract from about £9.2m to £8.5m.
It includes £293,368 that would be saved by fitting "aluminium cladding in lieu of zinc cladding".It includes £293,368 that would be saved by fitting "aluminium cladding in lieu of zinc cladding".
The switch allowed for a change of colour, but the BBC has been told another key reason was to save money.The switch allowed for a change of colour, but the BBC has been told another key reason was to save money.
Documents seen by the Times newspaper, reportedly show that, days earlier, the local management organisation had sent an "urgent nudge email" to the construction consultants involved in the refurbishment.Documents seen by the Times newspaper, reportedly show that, days earlier, the local management organisation had sent an "urgent nudge email" to the construction consultants involved in the refurbishment.
It says the email urged them to provide "good costs" on cladding that could be shown to the councillor overseeing the work.It says the email urged them to provide "good costs" on cladding that could be shown to the councillor overseeing the work.
Earlier planning documents suggest the original plan was for zinc cladding with a fire-retardant core.Earlier planning documents suggest the original plan was for zinc cladding with a fire-retardant core.
Residents had also been told their new cladding would be made of zinc. Despite their differences, both types of cladding have the same official fire rating.Residents had also been told their new cladding would be made of zinc. Despite their differences, both types of cladding have the same official fire rating.
Police investigating the disaster have said the tower's cladding has subsequently failed safety tests.Police investigating the disaster have said the tower's cladding has subsequently failed safety tests.
The savings were part of an ongoing effort by the council and the local tenant management organisation to drive down the cost of the refurbishment.The savings were part of an ongoing effort by the council and the local tenant management organisation to drive down the cost of the refurbishment.
A source close to one of the many companies involved in the project said the change was typical of constant pressure by councils to reduce the costs of building refurbishments.A source close to one of the many companies involved in the project said the change was typical of constant pressure by councils to reduce the costs of building refurbishments.
Council minutes from 2013 show dissatisfaction with the initially-preferred contractor for not keeping the scheme within budget.Council minutes from 2013 show dissatisfaction with the initially-preferred contractor for not keeping the scheme within budget.
Further bids were invited, and this led to the appointment of a different contractor in 2014 which was then asked to make savings including on the cladding.Further bids were invited, and this led to the appointment of a different contractor in 2014 which was then asked to make savings including on the cladding.
Kensington and Chelsea London Borough Council has promised to co-operate fully with all investigations into the fire.Kensington and Chelsea London Borough Council has promised to co-operate fully with all investigations into the fire.
Cladding failuresCladding failures
Tests are being carried out on 600 buildings around the country following the fire on 14 June.Tests are being carried out on 600 buildings around the country following the fire on 14 June.
On Friday, Downing Street said cladding from 149 tower blocks in 45 local authority areas had failed fire safety tests.On Friday, Downing Street said cladding from 149 tower blocks in 45 local authority areas had failed fire safety tests.
Every panel tested had failed combustibility tests, it added.Every panel tested had failed combustibility tests, it added.
An expert panel set up in the wake of the fire said cladding that has failed safety tests may still be allowed to stay attached to high-rise blocks.An expert panel set up in the wake of the fire said cladding that has failed safety tests may still be allowed to stay attached to high-rise blocks.
The Independent Advisory Panel said it would ask experts whether the material could stay on a building "under certain approved circumstances".The Independent Advisory Panel said it would ask experts whether the material could stay on a building "under certain approved circumstances".
► What happened at Grenfell Tower?► What happened at Grenfell Tower?
Lord Porter, chairman of the Local Government Association, said fire safety tests on cladding from high-rise buildings were flawed.Lord Porter, chairman of the Local Government Association, said fire safety tests on cladding from high-rise buildings were flawed.
He criticised the tests for focusing on the core of the panel - rather than the panel as a whole.He criticised the tests for focusing on the core of the panel - rather than the panel as a whole.
He told BBC Radio 4's Today programme that "isn't the right thing to test", adding: "The government needs to listen to a wider set of opinions and not just the experts they have got."He told BBC Radio 4's Today programme that "isn't the right thing to test", adding: "The government needs to listen to a wider set of opinions and not just the experts they have got."
Number 10 said the government was urging councils to carry out their own safety checks and to put mitigation measures in place where there are concerns.Number 10 said the government was urging councils to carry out their own safety checks and to put mitigation measures in place where there are concerns.
Meanwhile, the Sports Ground Safety Authority (SGSA), which monitors safety conditions at Premier League and Football League grounds, has written to football clubs across the country to ask them to check on any external cladding on stadiums.Meanwhile, the Sports Ground Safety Authority (SGSA), which monitors safety conditions at Premier League and Football League grounds, has written to football clubs across the country to ask them to check on any external cladding on stadiums.
Are you affected by or do you have knowledge of the issues raised in this piece? Let us know by emailing haveyoursay@bbc.co.ukAre you affected by or do you have knowledge of the issues raised in this piece? Let us know by emailing haveyoursay@bbc.co.uk
You can also contact us in the following ways:You can also contact us in the following ways:
Or use the form belowOr use the form below