This article is from the source 'bbc' and was first published or seen on . It last changed over 40 days ago and won't be checked again for changes.
You can find the current article at its original source at http://www.bbc.co.uk/news/business-36903904
The article has changed 13 times. There is an RSS feed of changes available.
Version 1 | Version 2 |
---|---|
Hinkley Point set to get final investment approval from France's EDF | Hinkley Point set to get final investment approval from France's EDF |
(about 2 hours later) | |
Investment in the new nuclear plant to be built in Hinkley Point, Somerset, is set to get final approval later on Thursday. | Investment in the new nuclear plant to be built in Hinkley Point, Somerset, is set to get final approval later on Thursday. |
The French utility, EDF - the company financing most of the £18bn project - is holding a board meeting at which it is expected to approve the investment. | The French utility, EDF - the company financing most of the £18bn project - is holding a board meeting at which it is expected to approve the investment. |
Following that agreement, legally-binding contracts will be signed and construction work can begin. | Following that agreement, legally-binding contracts will be signed and construction work can begin. |
It will be the UK's first new nuclear power plant in more than 20 years. | It will be the UK's first new nuclear power plant in more than 20 years. |
EDF hopes to have more than 2,500 workers on site by next year. | EDF hopes to have more than 2,500 workers on site by next year. |
Hinkley Point C is expected to provide 7% of the UK's total electricity requirement. | |
Costs | Costs |
The project has been hit in recent months by concerns about EDF's financial capacity. | The project has been hit in recent months by concerns about EDF's financial capacity. |
While one third of the £18bn cost of the project is being met by Chinese investors, Hinkley Point would remain an enormous undertaking for the stressed French company. | While one third of the £18bn cost of the project is being met by Chinese investors, Hinkley Point would remain an enormous undertaking for the stressed French company. |
Earlier this week EDF shareholders approved plans to issue new shares to raise 4bn euros (£3.4bn) to help pay for the project. | Earlier this week EDF shareholders approved plans to issue new shares to raise 4bn euros (£3.4bn) to help pay for the project. |
The French state, which owns 85% of EDF, will buy €3bn worth of new shares in the fundraising. | The French state, which owns 85% of EDF, will buy €3bn worth of new shares in the fundraising. |
Ahead of the decision, EDF said Hinkley Point was a "unique asset for French industry as it would benefit the whole of the nuclear industry and support employment in major companies and smaller enterprises in the sector". | Ahead of the decision, EDF said Hinkley Point was a "unique asset for French industry as it would benefit the whole of the nuclear industry and support employment in major companies and smaller enterprises in the sector". |
Although French unions are urging the company to push back the decision until the company is in a better financial position, UK unions have welcomed the project. | Although French unions are urging the company to push back the decision until the company is in a better financial position, UK unions have welcomed the project. |
"We urge the EDF board to give the financial go-ahead on a project which will generate thousands of decent skilled jobs and help meet the energy needs of the UK for generations to come," said Unite national officer for energy Kevin Coyne. | "We urge the EDF board to give the financial go-ahead on a project which will generate thousands of decent skilled jobs and help meet the energy needs of the UK for generations to come," said Unite national officer for energy Kevin Coyne. |
"The cost of not doing so could result in the lights going out in Britain and the West Country missing out on the much-needed economic boost which this major infrastructure project would bring." | "The cost of not doing so could result in the lights going out in Britain and the West Country missing out on the much-needed economic boost which this major infrastructure project would bring." |
Environmentalists are concerned about the plan. Greenpeace said there wasn't "a shred of evidence that Hinkley can be built on time or on budget, and if it hits the same problems as its predecessors, it can't be relied on to keep the lights on in the UK". | Environmentalists are concerned about the plan. Greenpeace said there wasn't "a shred of evidence that Hinkley can be built on time or on budget, and if it hits the same problems as its predecessors, it can't be relied on to keep the lights on in the UK". |
The campaign group added that more investment for renewable energy like offshore wind was needed. | The campaign group added that more investment for renewable energy like offshore wind was needed. |
Hinkley Point timeline | Hinkley Point timeline |
Jan 2006 - Government proposes nuclear as part of future energy mix | Jan 2006 - Government proposes nuclear as part of future energy mix |
Mar 2013 - Construction of Hinkley Point approved | Mar 2013 - Construction of Hinkley Point approved |
Oct 2013 - UK government agrees £92.50 per megawatt-hour will be paid for electricity produced at the Somerset site - around double the current market rate at the time | Oct 2013 - UK government agrees £92.50 per megawatt-hour will be paid for electricity produced at the Somerset site - around double the current market rate at the time |
Oct 2015 - EDF signs investment agreement with China General Nuclear Power Corporation (CGN) | Oct 2015 - EDF signs investment agreement with China General Nuclear Power Corporation (CGN) |
July 2016 - EDF board meets on 28 July to consider final investment decision | July 2016 - EDF board meets on 28 July to consider final investment decision |